EARTH & SPACE / PROGRAM ATLAS

Planning estimate ·

Earth Program Reality Report

A shared test lab, one instrumented site and one small hydrogen marine demonstrator, followed by a first series of five vessel conversions.

Through the first production series
95–270 million NOK
4–7 years from funded start
Initial research phase
NOK 7–16 million

Cost and schedule

Each phase adds cost and time. The schedule starts with funding and access to partners and facilities. Figures are in 2026 Norwegian kroner.

Incremental cost and time by phase, including 20% reserve
PhaseOutputDurationNOK million
Research and validationOne set of independently reviewed test results for SERAT, telemetry and a hydrogen integration concept.12 months7–16
Development and demonstrationAn integrated SERAT test installation at one existing site and a ZP-1-derived demonstrator on a partner hull.12–36 months46–132
First production seriesFive repeat small-vessel conversions on partner-supplied hulls, subject to approval of the demonstrator design.24–36 months42–120
Total through the first series4–7 years95–270

Research and development through the first demonstration total about NOK 53–148 million over 2–4 years.

Research and validation Work items & criteria to proceed
Work items before reserve
Cost itemBasisNOK million
Systems engineering and modelling3–5 full-time-equivalent years at NOK 1.4–1.8m each, including overhead.4.2–9
Bench hardware and test accessPower and heat emulation, instrumentation, data recording and shared lab time.1.2–3
Independent review and supplier workHazard review, scope definition and first supplier quotations.0.6–1.5
Subtotal before reserve6.0–13.5

Before proceeding. Define the host site and vessel, measure heat and power flows, and demonstrate safe local isolation under injected faults.

Development and demonstration Work items & criteria to proceed
Work items before reserve
Cost itemBasisNOK million
Design, integration and controls12–26 full-time-equivalent years at NOK 1.5–2m each.18–52
Site rig and demonstrator hardwareHeat recovery, protected distribution, an existing hull conversion and hydrogen-system hardware.12–36
Facilities and instrumented trialsShared test facilities, berth access, fuel logistics, onshore commissioning and trials.5–12
Safety, survey and qualification workIndependent acceptance work and evidence for an agreed prototype qualification pathway.3–10
Subtotal before reserve38–110

Before proceeding. Complete fault-injection, pressure and thermal tests. Agree the vessel’s qualification and trial plan with the relevant reviewers before any passenger service.

First production series Work items & criteria to proceed
Work items before reserve
Cost itemBasisNOK million
Recurring conversion and installationFive builds at NOK 5–14m each for hardware, installation and factory acceptance.25–70
Tooling and supplier qualificationRepeatable fixtures, documentation, quality checks and small-lot setup.6–18
Series acceptance and trialsSurvey, repeat trials and design-approval support for the agreed configuration.4–12
Subtotal before reserve35–100

Before proceeding. Release the repeatable configuration after trial evidence, supplier commitments and approval of the operating and maintenance plan.

What the Earth Program can build

The budget starts with protected power and heat recovery at an existing site and one hydrogen marine demonstrator. Applying for a full vehicle approval or building a new energy facility would require its own design, development and production budget.

Earth projects and the work that can be estimated
ProjectPriceable scopeWhat determines the next budget
SERAT Energy Island, LSI and resilient facilitiesIncluded in the staged estimate. An existing site can host grid-powered tests of heat recovery, monitoring, backup loads and local isolation. SafeSpots, infrared inspection and training can use the same site.Measure useful recovered heat and energy use, uptime, sensor reliability and isolation under faults. A hospital build or multi-site deployment needs a separate site and service specification.
ZP-1 and ZB-1 marine mobilityThe budget includes a ZP-1-derived prototype and five conversions on partner-supplied hulls. The direct build allowance is NOK 5–14m per conversion, before series setup, trials and reserve.The vessel survey, fuel storage, integration and onshore hydrogen supply drive cost. ZB-1 could reuse qualified subsystems after its separate duty and safety assessment. The EU FLAGSHIPS demonstration project lists €6.77m in total project costs. [1]
ZC-1 hydrogen combustion carOptional NOK 24–67m over roughly 2–3 years for a donor-platform test mule. The scenario allows 8–18 specialist years at NOK 1.5–2m each, NOK 8–20m for the donor vehicle, integration hardware and tests, and 20% reserve.Size the production programme after crash and storage integration, NOx measurement, refuelling compatibility and the vehicle approval plan. Supplier quotes and annual volume would be needed for a production unit price.
ZA-P01 and ZH-1 hydrogen aviationOptional ground-demonstrator scenario of roughly NOK 100–370m over 3–5 years. This assumes a shared propulsion test programme of 30–75 specialist years at NOK 1.5–2m each, NOK 40–160m for facilities, hardware and test work, and 20% reserve.Aircraft-specific installation, flight testing and approval follow the ground evidence. The EU’s HYDEA hydrogen aviation demonstrator lists about €105m in total project costs and runs from 2023 to 2027. [2]
ZA-1 passenger jet and ZCS-1 cruise shipComponent studies, design reviews and existing-platform demonstrations are the priceable steps today.A full newbuild requires a stable payload and range specification, a production partner, test and approval plans, infrastructure requirements and a defined order volume. These inputs determine both development and unit costs.
Fusion Power Facility and GENI InverseThe base budget covers conventional emulation of the SERAT energy interface. Coil, sensing and plasma diagnostics experiments can be scoped with a laboratory.ZENIT’s design targets are 5.30 GWth at the core and 2.00 GWe at the grid. A grid plant estimate needs evidence for net power, materials and maintainability, plus a site-specific licensing basis. Estimating Inverse field hardware requires repeatable physical measurements of a defined protective effect. [3] [4]
Norak Earth landing baseSurvey work, simulation and an instrumented ground mock-up are work a partner could scope.Platform construction depends on demonstrated vehicle loads, propulsion and landing performance. A site, allowable loads and a service plan are needed to obtain construction quotes.

The two optional demonstrator estimates are independent projects. Shared staff and test infrastructure would need to be reconciled before combining budgets.

Basis and uncertainty

Staffing and hardware

Loaded staffing assumptions are NOK 1.4–2m per full-time-equivalent year, depending on the phase. Hardware, lab access and trials are separate allowances. The scenario assumes available partner facilities and hulls. Adding ten specialist years at the development rate adds NOK 15–20m before reserve.

Budget boundary

The estimate covers one demonstration programme and a first conversion series. New hull acquisition, permanent fuel infrastructure, commercial operations, financing, VAT and escalation require separate budgeting. The low and high cases combine work-item ranges and add 20% reserve. Totals are rounded and the ranges express scenarios with no assigned probability. A larger redesign could push costs beyond them. [5]

What would tighten the estimate. A named host site and vessel, a measured energy balance, supplier quotations for storage and integration, and a written test and approval plan. The biggest schedule dependency is access to the host and qualified test facilities.

Sources

External figures retain their published currency and project scope. ZENIT figures are estimates for the scenarios above.

  1. European Commission, FLAGSHIPS. Total project costs for a hydrogen fuel-cell vessel demonstration programme. CORDIS project factsheet
  2. European Commission, HYDEA. Cost and dates of a hydrogen combustion propulsion technology demonstrator. CORDIS project factsheet
  3. U.S. Department of Energy, Milestone-Based Fusion Development Program. The initial $46m obligation across eight teams covered the programme’s first 18 months. DOE programme update
  4. ITER, July 2024 baseline proposal. ITER reported a proposed €5bn in additional cost to its organisation, then under member review. This was a revision to an experimental programme budget. ITER baseline briefing
  5. U.S. Government Accountability Office, Cost Estimating and Assessment Guide. Method reference for breaking costs into work items and recording assumptions and uncertainty. GAO guide
  6. The ZENIT Program’s Earth project register provides the concept scope used in this report. ZENIT Earth projects